The Software Modernization team proposes a two-year plan to prove the NDSL technology at scale on NASA's GEOS flagship model. The timeline of the project goes as follows:
timeline
title 24-26 Project
section Milestone 1 (M1) <br>
August 24 : Project kickoff : M1 tasklist frozen
November 24: [16-22 November] <br> All team attends SC24
December 24: [9-13 December] <br> Two team members attends AGU24
January 25 : M1 Review : Dynamical core FP-ready : Moist physics validating : CPU performance progress : Target metrics refined and documented
section Milestone 2 (M2) <br>
February 25 : M2 tasklist frozen
July 25 : M2 Review : Integrated and accelerated moist physics : CPU Performance : TBD...
section Milestone 3 (M3) <br>
August 25 : M3 tasklist frozen
January 26 : M3 Review : TBD...
section Milestone 4 (M4) <br>
January 26 : M4 tasklist frozen
August 26 : M4 Review: Full project post-mortem : TBD...
Kanban board and full project breakdown available on Github project
Any questions please email: [email protected]
- Supercomputing 23 (November 2023)
- Validation and benchmark of the Pace model, seeding project to the 24-26 project at NASA