These are guidelines around when Spring Security will be released. We favor pragmatism to sticking strictly to the rules.
-
Spring Security releases the second Friday of the month. If a release happens over a holiday, then we will do it the following Monday.
-
We have two GA releases a year labeled GA-1 and GA-2
-
If an RC2 is necessary, we will release RC2 two weeks after RC1
-
Regularly scheduled patch releases occur every other month
-
There may be circumstances (i.e fixing a CVE) where an extra release is performed.
# | Month | GA-1 | GA-2 | Patch |
---|---|---|---|---|
01 |
Jan |
M1 |
X |
|
02 |
Feb |
M2 |
||
03 |
March |
M3 |
X |
|
04 |
April |
RC1 |
||
05 |
May |
GA |
X |
|
06 |
June |
|||
07 |
July |
M1 |
X |
|
08 |
Aug |
M2 |
||
09 |
Sept |
M3 |
X |
|
10 |
Oct |
RC1 |
||
11 |
Nov |
GA |
X |
|
12 |
Dec |