EconomicDispatch_GeneratorPower_Costs.m
115 lines (81 loc) · 2.46 KB
/
EconomicDispatch_GeneratorPower_Costs.m
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100
101
102
103
104
105
106
107
108
109
110
111
112
113
114
115
%Punto 1: Despacho económico, demanda de 420 MW
Pdemand =420;
L = (Pdemand+5/0.016+5.5/0.018+4.5/0.014)/(1/0.016+1/0.018+1/0.014);
a1=290; b1 =5; y1=0.008;
a2=270; b2 =5.5; y2=0.009;
a3=300; b3 =4.5; y3=0.007;
min1 = 100; max1=300;
min2 = 200; max2=350;
min3 = 175; max3=400;
%Calculo costo con menor potencia de generación
C1min = a1+ b1*min1+ y1*min1^2;
C2min = a2+ b2*min2+ y2*min2^2;
C3min = a3+ b2*min3+ y3*min3^2;
%Cálculo de 2 Generadores
%---G1 y G2 ---%
L_12=(Pdemand+b1/(2*y1)+b2/(2*y2))/(1/(2*y1)+1/(2*y2));
P1_12 = (L_12-b1)/(2*y1);
P2_12 = (L_12-b2)/(2*y2);
C1_12 = a1+ b1*P1_12+ y1*P1_12^2;
C2_12 = a2+ b2*P2_12+ y2*P2_12^2;
C_12 = C1_12+C2_12;
%---G1 y G3 ---%
L_13=(Pdemand+b1/(2*y1)+b3/(2*y3))/(1/(2*y1)+1/(2*y3));
P1_13 = (L_13-b1)/(2*y1);
P3_13 = (L_13-b3)/(2*y3);
C1_13 = a1+ b1*P1_13+ y1*P1_13^2;
C3_13 = a3+ b3*P3_13+ y3*P3_13^2;
C_13 = C1_13+C3_13;
%---G2 y G3 ---%
L_23=(Pdemand+b2/(2*y2)+b3/(2*y3))/(1/(2*y2)+1/(2*y3));
P2_23 = (L_23-b2)/(2*y2);
P3_23 = (L_23-b3)/(2*y3);
C2_23 = a2+ b2*P2_23+ y2*P2_23^2;
C3_23 = a3+ b3*P3_23+ y3*P3_23^2;
C_23 = C2_23+C3_23;
%----2. Demanda 630 MW-----
Pdemand2 = 630;
L2 = (Pdemand2+b1/(2*y1)+b2/(2*y2)+b3/(2*y3))/(1/(2*y1)+1/(2*y2)+1/(2*y3));
P2_1 = (L2-b1)/(2*y1);
P2_2 = (L2-b2)/(2*y2);
P2_3 = (L2-b3)/(2*y3);
%--iteración 2--
P2_2fix =200;
deltaP2_1 = Pdemand2-(P2_1+P2_2fix+P2_3);
deltaL = deltaP2_1/(1/(2*y1)+1/(2*y3));
L2_2 = L2+ deltaL;
P2_2_1 = (L2_2-b1)/(2*y1);
P2_2_3 = (L2_2-b3)/(2*y3);
C2_2_1 = a1+ b1*P2_2_1+ y1*P2_2_1^2;
C2_2_2 = a2+ b2*P2_2fix+ y2*P2_2fix^2;
C2_2_3 = a3+ b3*P2_2_3+ y3*P2_2_3^2;
%Costo total
C2_2 = C2_2_1+C2_2_2+C2_2_3;
%----2. Demanda 970 MW-----
Pdemand3 = 970;
L3 = (Pdemand3+b1/(2*y1)+b2/(2*y2)+b3/(2*y3))/(1/(2*y1)+1/(2*y2)+1/(2*y3));
P3_1 = (L3-b1)/(2*y1);
P3_2 = (L3-b2)/(2*y2);
P3_3 = (L3-b3)/(2*y3);
%Iteración 2
P3_1fix =300;
deltaP3 = Pdemand3-(P3_1fix+P3_2+P3_3);
deltaL = deltaP3/(1/(2*y2)+1/(2*y3));
L3_2 = L3+ deltaL;
P3_2_2 = (L3_2-b2)/(2*y2);
P3_2_3 = (L3_2-b3)/(2*y3);
%Iteración 3
P3_3fix =400;
deltaP3_2 = Pdemand3-(P3_1fix+P3_2_2+P3_3fix);
deltaL2 = deltaP3_2/(1/(2*y2));
L3_3 = L3_2+ deltaL2;
P3_3_2 = (L3_3-b2)/(2*y2);
C3_3_1 = a1+ b1*P3_1fix+ y1*P3_1fix^2;
C3_3_2 = a2+ b2*P3_3_2+ y2*P3_3_2^2;
C3_3_3 = a3+ b3*P3_3fix+ y3*P3_3fix^2;
%Costo total
C3_3 = C3_3_1+C3_3_2+C3_3_3;
Zpos= 0.25j;
Zneg = 0.13j;
Zcero = 0.15j;
Z_tri = 1 /0.25